This project went out to bid on May 8, 2019; bid opening on June 11, 2019. The Notice to Proceed was June 24, 2019 and completion date was April 2020. The contractor for this project was Colacurcio Brothers, Inc. The final cost of the project was $5,028,320.01, including tax and change orders.